N11 Gorey to Enniscorthy PPP Scheme

N11 Gorey to Enniscorthy PPP Scheme


Project overview

Detailed topographical survey and checking of control prior to the start of construction.  The survey consisted of surveying 16.5 kms of roads, 15 kms of watercourses and 50 hectares of infill survey in overgrown areas. The surveys were carried out over a 40 km corridor from the N11 Frankfort round about to the N11 tie-in point south of Enniscorthy. The project was surveyed and delivered within 6 weeks from starting on site.


Project solution

  • Surveys carried out utilising a variety of methods and technologies including using Trimble S6 robotic total stations and Trimble R10 GNSS receivers.
  • The survey included working on live roads including the N11. All surveys were carried in compliance with Chapter 8 traffic management regulations.
  • Multiple teams were deployed to site at short notice to ensure the project was delivered on time.
  • We also checked if existing survey control was still in situ and installed new survey control if needed.

Project delivery

  • 3D AutoCAD 1:500 topographical survey plans.
  • 3D AutoCAD 1:500 water course surveys including section photos.

Gallery

Click images to expand.